Planners,
I work in the overhead line transmission industry, this mainly depends on client outages in order for us to carry out work.
So basically as soon as an outage begins we can start work on the refurbishment of conductors etc, we have a set time to which the outage will run so all work to do with the outage has to be completed by outage finish.
In my programme I show all pre outage works, ie steelwork replacement as well. The last activity in the pre outage works may have some float before the outage starts. Then the outage works begins.
When the outage finishes there will be other work to do like reinstatement of sites etc.
My question is, how do we show that outage? I did have the outage represented by a start and finish milestone, the problem was that the critical path only ran from my outage finish mielstone to the project end. I need to show the critical path through out the project ie design>procurement>construction
What would the best way to maintain having a critical path and showing the outage?
first i don't recommend to use contraints to indicate outages.
I always use an outage calendar that shows the outage(s) duration as a work days and all other days as nonwork.
to adjust the critical path you will have to revisit the pre-outage activities to revise the durations and logic, see if it's possible to use FS instead of paralel logic also check if the durations are enough.
and if everything is okay sometimes i extend the durations to adjust the critical path and make it look like the longest path.
Hi John
I solved this problem by putting the outage work as the only "working" period in a non working calendar.
This project was a start up and linkage of a new sub station in central london and the only time sections of the grid could be switched of was for 90 minutes from 21:00 hours on a Friday night.
So my calendar had this work pattern for every week - if you missed the slot then wait for next week.
I am not sure that P6 is subtle enough to replicate this work pattern - P3 certainly wasn't - so you may have to resort to Asta PowerProject.
Best regards
Mike Testro