planned,49 high rise buliding with a footprint area/floor=2200sqm, ratio helper to skilled is 1:3.33
formworks works only
Hi Alain
What is the ratio of Skilled to Helper and what type of structure is it?
Best regards
Mike Testro
on formworks (scaffolding,phenolic boards, aluma system)= leadman=0.75/day, skilled=10/day, helper=3/day, units is sq.m
hope it helps.
Hi Kier,
Have you got any technical figures about scaffolding productivity.
Tarek Barham