Why is that some people believe you cannot use Physical percent complete if the schedule is not resource-loaded?

M
Matt Ir 👤 Member for 14 years 6 months

Why is that some people say: you can not use Physical percent complete on this schedule because it is not resource-loaded ?

As far as I know, Physical percent complete for the activities has nothing to do with the cost,except for calculation of WBS percent complete field which needs the cost and resource data.

can anyone help clear out this confusion?

Thank you

S
sadegh usman 👤 Member for 15 years 1 month

This is confusing,but the basis of your physical % completion, can be check through cash % complete..their is discripancy but tolerable only..

Thanks,

 