Hi,
How do I get the activities in-progress and activities which are going to start in next 2 weeks using Primavera? Thanks for your help.
Thanks,
Pradyumna
Hi,
How do I get the activities in-progress and activities which are going to start in next 2 weeks using Primavera? Thanks for your help.
Thanks,
Pradyumna
Hi,
Right Click on Window. Click on Filters - Click on New.
Enter Fliter name as 2 Weeks Look ahead
After that enter the parameters shown below
where - start - is within range of - DD - DD+2W
Or - Activity status - equals - In progress
Mark Click on 2 weeks look head.
Then you will get activity in progress for next 2 weeks.
Hope you will get the solution.