I need some guidelines for doing a ship impact protection system project programme. The major
activities includes construction of two berths and a fender system for the ship impact protection.
What are the major concerns while planning a programme for this work, berth construction includes
piling works also. Expecting your valuable view points,
With Regards,
Sunil.
Hi Mike,
Thanks a lot for your valuable reply. In case of SIPS piling method what productivity
rate are we following? ,Thanks in advance for your reply..
Best Regards,
Sunil.
Hi Sunil
Piling will probably be done from an ofshore barge.
If so then you have to consider:
State of the tide
Wave configuration
Weather - monsoon
Support and supply tenders
When piling is in progress the rest of the work can follow for the jetty deck and top beams.
After that you will have normal access.
Best regards
Mike Testro