Ship impact protection system

S
Sunil Babu 👤 Member for 15 years 6 months

Dear all,

   I need some guidelines for doing a ship impact protection system project programme. The major

   activities includes construction of two berths and a fender system for the ship impact protection.

   What are the major concerns while planning a programme for this work, berth construction  includes

   piling works also.  Expecting your valuable view points,

   With Regards,

           Sunil.

S
Sunil Babu 👤 Member for 15 years 6 months

Hi Mike,

Thanks a lot for your valuable reply. In case of SIPS piling method what productivity

rate are we following? ,Thanks in advance for your reply..

Best Regards,

Sunil.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Sunil

Piling will probably be done from an ofshore barge.

If so then you have to consider:

State of the tide

Wave configuration

Weather - monsoon

Support and supply tenders

When piling is in progress the rest of the work can follow for the jetty deck and top beams.

After that you will have normal access.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts