When I tried to import Excel file into Primavera P6 Release 7 , the final window of importing (Select the project you would like to import the Excel into it) did not show any projects to be selected.
I guess this could be due to limited rights or OBS/EBS organizing, but I could not reach out how to solve it.
When I tried to import Excel file into Primavera P6 Release 7 , the final window of importing (Select the project you would like to import the Excel into it) did not show any projects to be selected.
I guess this could be due to limited rights or OBS/EBS organizing, but I could not reach out how to solve it.
If you have 9000activities based categories assign the resources by selcting that sort of multipile activites like all steel activities select and assign the required resources. Later export to excel and readjust the bq and import back
1) As Rodel mentioned, resource import in excel will not work. You have then to define your resources in the global database (Enterprise -> Resource->... ), defining the resource type, details and unit/price as required..
2) Now, if you wish to do import, use the resource assignment module; export from your project a resource assignment template; then assign your resources thru exce to the template; Your file is ready for import, subject to the file size limitations.
You can not import a Resource if you dont have an open project or where you want to put this resource to your project. Just try using SDK (Software Development Kit) for you to add Resources even without an open project.
P6.1 Resource import function in excel doesn’t work but resource Assignment is working fine. You have to use Excel SDK (Dictionary6.xls)
PMRef Guide:
"In the Project Management module, users cannot import any global data that does not currently exist in the Project Management database, such as resources, codes, cost accounts, and so on."
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
make sure that you have the rights to do this and click on the 3 little dots in the lower rigth hand corner of the box
Dears
When I tried to import Excel file into Primavera P6 Release 7 , the final window of importing (Select the project you would like to import the Excel into it) did not show any projects to be selected.
I guess this could be due to limited rights or OBS/EBS organizing, but I could not reach out how to solve it.
Any suggestion to solve it.
Dears
When I tried to import Excel file into Primavera P6 Release 7 , the final window of importing (Select the project you would like to import the Excel into it) did not show any projects to be selected.
I guess this could be due to limited rights or OBS/EBS organizing, but I could not reach out how to solve it.
Any suggestion to solve it.
If you have 9000activities based categories assign the resources by selcting that sort of multipile activites like all steel activities select and assign the required resources. Later export to excel and readjust the bq and import back
I have around 9000 activities. can i assign resources to all activities. What is the limitation
Roozbeh, just to complete my posting below:
1) As Rodel mentioned, resource import in excel will not work. You have then to define your resources in the global database (Enterprise -> Resource->... ), defining the resource type, details and unit/price as required..
2) Now, if you wish to do import, use the resource assignment module; export from your project a resource assignment template; then assign your resources thru exce to the template; Your file is ready for import, subject to the file size limitations.
As you said, "Maybe I am not using a correct procedure for importing resources.". - and that is true.
Roozbeh,
You can not import a Resource if you dont have an open project or where you want to put this resource to your project. Just try using SDK (Software Development Kit) for you to add Resources even without an open project.
Hope this can help
From where can we download the Excel SDK?
From where can we download the Excel SDK?
Roozbeh,
P6.1 Resource import function in excel doesn’t work but resource Assignment is working fine. You have to use Excel SDK (Dictionary6.xls)
PMRef Guide:
"In the Project Management module, users cannot import any global data that does not currently exist in the Project Management database, such as resources, codes, cost accounts, and so on."