Total Float Problem in P6

Greetings,

I have developed a project schedule using P6 v7, with a total float -15 days, when I do 2 weeks lookahead filter, I can see that some activities have positive float and some activities have negative float, the problem is that the total Float for all the project is showing the positive float only! it is neglecting the nagtive float! Why????

 

Kindly advise.

A
Abilash Palakkadan Mathew 👤 Member for 13 years 9 months

 

Negative float is shown usually when you have finish constrain, the activities which are not in the critical path will have positive float.