Data Date Time

M
Mike Testro 👤 Member for 20 years 6 months

Hi All

I was reviweing a contractor's schedule as part of a delay analysis exercise when I noticed that the time set on the data date progress line was 08:00.

The work calendar is due to start on 07:00 so for every progress report one hour is lost on the programme.

It could have been much worse if the data date time was 12:00.

I suggest that the time on the data date is set earlier than the dominant work patter start time.

Best regards

Mike Testro

R
Ronald Winter 👤 Member for 23 years 5 months

Oracle/Primavera’s definition of a Data Date is the first moment that new work is able to start or resume.  It is not the same thing as a status date. 

In Mike’s example, he is quite correct to request that the Data Date be set to 07:00.  I believe that P6 automatically sets it to 08:00 as a default.

G
Gary Whitehead 👤 Member for 17 years 3 months

Hi Mike,

 

I've always worked on the basis that the data date (& time) should be set to the last point for which you have progress information.

Hence if dominant work pattern finished at 6pm on a friday, my data date for a weekly update would be 6pm on a friday

 

Cheers,

 

G

Forum Sponsor

Top Posters

Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts