Same calendar for activities AND resources?

J
Jenny Ingco 👤 Member for 14 years 4 months

Dear Planners,

How I can assign same calendar for my activities AND resources? Because when I go to resourse calender there is no option to use project calender there are only Global and resourse calenders. So, do I need to greate new calender in the Global and make it exactly same the one in project calender? I am using P6 v.7..

Thank you for any advise,

 

Hanson

 

J
Jenny Ingco 👤 Member for 14 years 4 months

Dear Shahlul,

Thank you very much for your help. I just was wondering how I can use same calendar for project activities and recourses.. Example if the construction calendar under project with 5 working days per week and 8hrs/day and recourses assigned to this activities can work 7 days per week that will cause problems in the schedule. So I believe we should create new calendar in recourses with same working days and hours in project calendar.

 Thank you,

 HANSON

S
Shah. HB 👤 Member for 17 years 6 months

Hi Hanson

Open the project you created and choose enterprise menu, select calendar option, where you can create calendar pertained to project specific.

Assign calendar to one activity first and then use fill down option to assign all the required activities

Cheers

Shahul

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts