Effect of Calendars on Task Links

R
Ronald Winter 👤 Member for 23 years 5 months

It is indeed true; MS Project uses the project default calendar for lags. P3 uses the predecessor activity’s calendar, and P3ec uses any calendar it wants to. Good luck!

B
Bernard Ertl 👤 Member for 23 years 6 months

There is a long discussion on the subject (albeit at a more general level) where it is easy to see that different scheduling packages handle multiple calendars and calendars for lag relationships very differently:



What do you expect?



I really did not wish to disclose which systems I was using, but since you have a direct question and a specific need, I will share that in my testing, it appeared that MS Project was indeed using the default project calendar for the lag relationships irrespective of the calendars for the predecessor or successor tasks. I did not attempt to import an existing schedule into another schedule using a different default calendar, but it would appear from your post that doing so does not change the calendar for the lag activities.



You might try exporting the most basic data possible and re-importing. Perhaps you can find a medium that does not communicate the calendars for relationships.



Bernard Ertl

eTaskMaker Project Planning Software

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts