Deal all:
I'd like to know if a baseline programme can have actual progress data ? because sometimes with a complicated ongoing project,we need to update the baseline programme,i.e adding some milestones/activities ,adjusting or revising some relationships / duration / start and finish date and so on.
If the project have been carried out for about 50%(actual progress) and we have updated the baseline programme on base of the old BLP , what i presume is that i have to input all the actual data once more time, that'd be a huge work if the number of activities is as many as 1000 or even more.
My question is that can i revise the data on base of the actual progress schedule and then assign a new BLP which include the actual progress data ? Is there anyone having experience about this issue.
Thanks in advance and take this opportunity to Wish all of you Merry Christmas and Happy New Year.
Shiguo
Hi
Yes, you can't have actual data in your BL even the project is actually started but what you can do is revise your old baseline according the contract change at the mid of project duration and submit it for approval.
Thank you,
Hanson
Raymund, Thanks for your reply.
Zhang,
See this link... it has answer to your queries.
http://www.planningplanet.com/forums/primavera-version-pm5-pm6/531127/h…
Zhang,
See this link... it has answer to your queries.
http://www.planningplanet.com/forums/primavera-version-pm5-pm6/531127/h…