Restricted dates (Potentially) How to handle them

Hi,

 

I am working on a project where there are many locations over a 70km stretch.  Some of these areas potentially have Endangered Animals in them and we cannot work During their mating season (Apr 15 to July 31) if the wildlife experts find any signs of the Endangered Animals in the area during that time.  All work will stop and we will not be able to continue until after July. 

I need to identify those locations so we can do our best to avoid scheduling no work during that time in those locations.  I tried using a calendar for wildlife issues but that did not work as I do not want the schedule dates to be changed I just want to be notified if we have work scheduled at that location at that time.

 

Can you please advise me, ....  should I use "issues"?  If so how?

 

Thank you

Mark

M
Mark Fairbairn 👤 Member for 13 years 6 months

Thanks Gary,

 

I used your suggestion and it meets my needs perfectly as I have 5 different variations on "wildlife issues"

 

I appreciate your help.

Mark

G
Gary Whitehead 👤 Member for 17 years 2 months

Mark:

 

1) Add a code to your activties "Potential Wildlife Issues?" (Y/N)

2) Create a filter where code = Y

3) Create a filter "Mating season" where Start is within April 15 to July 31 OR Finish is within April 15 to July 31

4) Apply both filters

 

Cheers,

G

M
Mike Testro 👤 Member for 20 years 6 months

Hi Mark

Set up non working days on different calendars and apply them to the required activities.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts