Renumbering activity ID's

B
Bob Foden 👤 Member for 18 years 8 months

Dear Planners

I'm trying to renumber all of the activity ID's in a plan I've copied from a previous project. I want the numbers to run sequentially through the various WBS in this new version but they appear to be renumbering to the same sequence as the original ie the order the activities were created. is there a way to override this ?

Thanks in advance

regards

Bob Foden

J
Johannes Vandenberg 👤 Member for 16 years 4 months

Hi Bob

In P6 7 is renumbering easy. Go to Edit and select tab "renumber activities". You have various options but you can create any number you desire.

Regards Johannes

 

S
shiguo zhang 👤 Member for 13 years 6 months

Dear Bob,

I don't know if it's right or not ,I suggest you setting  the sequence of all activities in only "sort" dialog box and  meanwhile deleting all the "group by"settings . You can renumber activities IDs  in the new layout after sorting activities by "WBS"and "start".

Please refer to the following image.[[wysiwyg_imageupload:1433:]]

Hope this will help.

Shiguo

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts