Dear Planners
I'm trying to renumber all of the activity ID's in a plan I've copied from a previous project. I want the numbers to run sequentially through the various WBS in this new version but they appear to be renumbering to the same sequence as the original ie the order the activities were created. is there a way to override this ?
Thanks in advance
regards
Bob Foden
Hi,
I write an article regarding How to Renumbering Activity ID in Primavera P6.
Kindly read it here : https://doduykhuong.wordpress.com/2016/05/27/renumbering-activity-id-in-primavera-p6/
Hi Bob
In P6 7 is renumbering easy. Go to Edit and select tab "renumber activities". You have various options but you can create any number you desire.
Regards Johannes
1-just group and sort by required activity codes/wbs or groups accroding to requirments
2-create ac id in excel and replace with globle change.
watch this video
http://www.youtube.com/watch?v=HdVvgtgCqSc
1-just group and sort by required activity codes/wbs or groups accroding to requirments
2-create ac id in excel and replace with globle change.
watch this video
http://www.youtube.com/watch?v=HdVvgtgCqSc
Dear Bob,
I don't know if it's right or not ,I suggest you setting the sequence of all activities in only "sort" dialog box and meanwhile deleting all the "group by"settings . You can renumber activities IDs in the new layout after sorting activities by "WBS"and "start".
Please refer to the following image.[[wysiwyg_imageupload:1433:]]
Hope this will help.