Extract Late budgeted labuor unit and Early budgeted labuor unit

Anyone help me how to Extract Late budgeted labuor unit  and Early  budgeted labuor unit  from  

P6.

K
Khaja Sharief 👤 Member for 17 years 9 months

You can get this information in three windows; (1) activity usage spreadsheet (2) Resource Usage Spreadsheet (3) Resource assignments.

In all the windows you can right click on the spreadsheet->Spreadfields->Customize->select the field either early or late. 

J
Johannes Vandenberg 👤 Member for 16 years 5 months

Hi Jay

I suggest to go to the Assignments at the left hand of your screen and use filters and group &  sort to make the selection you desire.

Regards

Johannes