I'd like to ask the experts about examples of a Schedule Variance Report. I need to present this type of report on a bi-weekly schedule review meeting with the client. What do you show on that kind of reports? (i.e. every variance between current update and previous update OR any specific filter, such as only negative variance, variance greater that 20 days, variance on the critical path, etc.?)
Schedule Variance Report in P6
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Raul,
If this report is just to be used at a bi-weekly client meeting, I would keep it brief -no more than 3 pages of A4.
I would include the following:
1) EV vs PV (SPI or SV) at overall project level, and at lower levels of the wbs, as appropriate
2) %age of the activities due to complete in the (bi-weekly) reporting period, that were completed on time or early
3) Any activities on the critical path that have slipped, with commentary covering: how much delay, root cause of delay, and corrective actions to recover delay
4) Any activities that have slipped, that also have a total float of less than the (two week) reporting period
5) Any activities that have slipped by more than 4 days in the period.
6) Any trends of activites or issues that appear in the above and in previous reports
7) Any issues or risks which might impact planned progress for the next period, with mitigations to be taken
The following article can provide you with some theory and examples of reports for project control. It applies no matter what software you use.
http://www.spiderproject.com/images/img/pdf/Project%20Control%20Methodologies.pdf
Best regards,
Rafael