Hello,
I have just started using Primavera P6 and I could use as much advice I could get. Well the problem is that i set an activity duration for 2 days , with working hours 8:00-16:00.What I have seen and do not understand is that while the activity was supposed to start the first day at 8:00 and finish the second day at 16:00, in fact it ends on the third day at 11:00.
Does anybody have an idea why is that happeing and how I can correct it?
Thanks,
George
second
Most likely the calendar you have assigned to the activity does not have the working day starting at 08:00 and finalizing at 16:00. Or the second day is a Holliday ?...in any case check calendar of thee activity or the calendar of the resource if any.
BR
JMFrade
.