"Composite" Timescale in MSP2010

Hi,

Hoping someone can help. I was wondering if MSP 2010 has the capability to show an "composite" timescale on the Gantt charts? By this, I mean something akin to P3 where you can showthe main timescale for the project duration on say a quarterly basis, but then expand the timescale over a 3 month period to show as a weekly timescale.

Thanks.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Tony,

unfortunately not; it is not possible to have such a composite timescale in MSP, whatever the version is; however it is easy to swith from quartely to monthly to daily by clicking on the Zoom In/Zomm Out magnifiers icons.