Problem in P6 Resource Usage Spreadsheet and Profile

Hi Guys,

I'm having a problem regarding the resource usage speadsheet and histogram (profile).

I'm experiencing this in my construction program, so i tried it in a one activity program and see if it still exists.

I have an activity with 7 days duration loaded with resource of 70 units linearly distributed. So it means I should have 10 units per day and at the end of the s-curve should have 70 units.

In the spreadsheet, everything is fine and correct. But in the histograme and s-curve it shows only 1 unit (actually it is 1d) and at the end of 7 days the s-curve have 9d. (by the way how to change or remove this "d" units?)

How to correct this problem?

Thanks

R
Raymund de Laza 👤 Member for 16 years 6 months

Ronn,

Check the setting for Resource Distribution Interval in User Preferences. It should match the Timescale display.

Unclick the "Show unit label" in the Preferences.

 

 

Regards,

Forum Sponsor

Top Posters

Viet Tran
8 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts