Productivity and Norms

T
TII WS 👤 Member for 16 years 4 months

Hi,

Need some assistance in buildig up the as built productivity.

I was thinking of classifying under such category as below

Excavation

Bored pile

Pilecap

Raft Slab

Ground beam

Column

Slab

Any idea what unit should I use if I were to build this in relation to resource usage as well. Should I use qty/day, or manday/qty or any other suitable unit ?

Any idea to improve on these? Or should I split further into rebar, formwork, etc

 

 

 

A
Andrew Tan 👤 Member for 21 years 8 months

Hi,

I will do so for my own project

Excavation - m3 / mday or m3 /eqpt

Bored pile - lm / mday

Pilecap - No./mday (not sure)

Raft Slab - m3 / mday or m3 /eqpt

Ground beam - m3 / mday or m3 /eqpt

Column - m3 / mday or m3 /eqpt

Slab - m3 / mday or m3 /eqpt

As most the building related work is related to concrete, we usually calculate using m3 / mday. If needed, m3 / eqpt to show the needs for concrete pumps, vibrators.

Will not split into rebar, formwork. Calculate these together in its entirety. Do take note of the 72 hours allowance for formwork stripping if needed.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts