Hello friends,
I have a initial project. And another one i have an updated project.
Now what i did is, in the initial project i added baseline from the option "convert the other project as baseline" and i assigned the updated project as a new baseline.
Unfortunately i deleted the updated project.
Now is there any possible way to extract the updated project which is assigned as baseline 1 to initial project?
Hope u understood my problem.
Kindly help with a way and advise.
Regards,
Sivaganesh.S
Urgent help - Project extraction from baseline
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Thanks Gary.
It really helped. Eastiest way. Thanks a lot.
And Rafael, I appreciate your reply, it was really an additional information. Thanks
Regards,
Sivaganesh,S
The easiest way would be to look on the Backup. A Backup of the project file that is performed on the background with no noticeable effect on computer speed as a full database backup of all projects takes too long to execute and slow down computer, also restoring database restore all. Once in a while a full backup using any backup utility [or your software] shall be performed.
I use autosave every 5 minutes, look for backup options in your software.
1) Open initial project
2) Go to Project > Assign baselines, and ensure your updated project is NOT selected as a project or user baseline
3) Go to Project > Maintain baselines, select the updated project, and click "restore".
It should now appear back in your EPS
NB: In the future, I advise to take a copy of any project you plan to use as a baseline, so that the original version remains in your EPS.
Cheers,
G