Earned Value in P6

J
John Sims 👤 Member for 15 years

Hi All,

Can anybody tell me what columns I should show when using EV in P6

Do i use planned cost or cum planned value cost?

I did think they was the same thing! But when exporting this data into an excel s curve chart my cum planned value is almost double of what my planned value is in my project in the month of October.

Anybody??

Cheers John

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

John,

Cumulative planned cost sums up the by period cost: by the end of week #2, cum cost equals week #1 + week #2 cost, and so on

Planned cost displays the value by period

it is therefore much better to export cost than cumulative cost; Excel will draw the S curve chart by agregating the individual values, on the contrary, if you want to produce a vertical bar chart in Excel, export the cumulative cost, as a bar chart is not cumulative by itself

Alexandre

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts