Time Impact Analysis needs sub-network or fragnets to be attached to a main schedule can it be done so in P6 webbased.
I can not see an Fragnet in the P6 that we access on our server.
Please let me know how to use fragnet concepts.
Time Impact Analysis needs sub-network or fragnets to be attached to a main schedule can it be done so in P6 webbased.
I can not see an Fragnet in the P6 that we access on our server.
Please let me know how to use fragnet concepts.
Hi Mike
No problem to call them "Fragnet <xy>"
They are stored within your database as normal projects. If you'll need them you just open the template/fragnet together and copy the activities. For me it seems easier to use.
Regards from Germany
Dieter
Hi Deiter
I never lose the capacity to be amazed by the way that Primavera conspires to make things difficult.
Every delay analyst following the AACE principles knows that you have to set up "Fragnets".
When are the AACE gurus going to change the text to "Templates" ?
At least with Asta PowerProject you can call them whatever you want - I prefer "Delay Impact Summary".
Best regards
Mike Testro
Hi
It seems that you are an experienced P3 user who is forced to use P6. As there are some differences within the domunentation a file is included: "Move from P3 to P6". At least you should read chapter "Part 1: Before you begin". This will make life easier for you.
Fragnets do no longer exist, but you can use templates instead. We created small projects for special purposes. To include them into projects is rather easy.
Good luck!
Dieter