Time Impact Analysis needs sub-network or fragnets to be attached to a main schedule can it be done so in P6 webbased.

I can not see an Fragnet in the P6 that we access on our server.

Please let me know how to use fragnet concepts.

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Mike

 

No problem to call them "Fragnet <xy>"

They are stored within your database as normal projects. If you'll need them you just open the template/fragnet together and copy the activities. For me it seems easier to use.

 

Regards from Germany

Dieter

M
Mike Testro 👤 Member for 20 years 6 months

Hi Deiter

I never lose the capacity to be amazed by the way that Primavera conspires to make things difficult.

Every delay analyst following the AACE principles knows that you have to set up "Fragnets".

When are the AACE gurus going to change the text to "Templates" ?

At least with Asta PowerProject you can call them whatever you want - I prefer "Delay Impact  Summary".

Best regards

Mike Testro

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi

It seems that you are an experienced P3 user who is forced to use P6. As there are some differences within the domunentation a file is included: "Move from P3 to P6". At least you should read chapter "Part 1: Before you begin". This will make life easier for you.

Fragnets do no longer exist, but you can use templates instead. We created small projects for special purposes. To include them into projects is rather easy.

Good luck!

Dieter 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts