submission and approvals prior to commencement date

C
Chris G. 👤 Member for 19 years 11 months

Dear PP experts,

I am developing a tender programme for a quite complex resort and hotel tower buildings in a tight completion timeframe.

The qusetion is, "Is it contractually acceptable to make any submission and approval request from the Engineer immediately after receiving LOA but prior to obtaining building permit/commencement date to speed-up things, for example enabling work subcon approval to be on board and mobilize immediately, technical documents, QA/QC, HSE, CEMP plan approvals...?"

Hope for your expert guidance.

Regards,

Chris

C
Chris G. 👤 Member for 19 years 11 months

Mr. Mike,

Appreciate your prompt response.

Regards,

Chris

M
Mike Testro 👤 Member for 20 years 6 months

Hi Chris

As soon as you get a LOA - provided it is drafted correctly - then the contract is active so Yes you can hit the deck running.

If the Engineer has not yet been appointed then you have your first grounds for an Eot before you have started.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts