Using the Fill Down Option In P6

R
Rhys Parry 👤 Member for 14 years 8 months

I have a calender setup that is showing standard for all my activities and what I want is to change them all to a 7 day working week.

I have added the column calender in and then I chose one activity with the 7 day a week in it, but it is not allowing me to select that column and fill down to all the others. (Fill Down option is greyed out)

 

Any Ideas

Thanks

N
Nilkamal Parikh 👤 Member for 16 years 10 months

Hi Siddic,

Please select all the activities which you want to change their IDs. Go to Edit and select renumber activity ids. You can see the manu which will allow you to change the activity ids by increasing its number, Auto number which you can assign what you want for new ids or just to replace beginning characters of your id.

Hope this will help.

Cheers

Nilkamal Parikh

S
Siddic K 👤 Member for 14 years 7 months

How to Change Activity ID in P6 without exporting to excel. Please help .....

R
Rhys Parry 👤 Member for 14 years 8 months

I got it working in the End thanks I thought It was selecting all of the columns but as you said if I click on the column i want to fill down and highlight the other rows it just fills that column.

 

All sorted

Thanks

J
James Mulhearn 👤 Member for 14 years 11 months

You do not need to select the column only the cell with the calendar info the hold the 'shift" key down and go to the cell at the bottom of the Calendar Column "click" on that cell and then fill down...

P6 highlites every thing but only fills down the column you are in , hope this helps...

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts