When we revising the baseline how we can make earned labour units equal to palnned labour and to bring remaining units as the remaining of earned hours to earn.
My reference is to P3, where, when we have actual data; planned data was getting converted to actuals and the remaining was continuous to what we earned till completion.
Revising Baseline
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Daniel, Thanks for the reply
Even after giving the actual dates and re baselining, P6 is considering the Original early start / finish dates to calculate the planned labor units; it is not considering the actual start date.
And observed the following
My requirement is, to get a curve from P6 showing earned value till data date and values planned for the upcoming weeks / estimate at completion till end date ( Remaining units should be equal to Budgeted units minus Earned units, and P6 should calculate it automatically, even if we don’t update actual units manually)
[[wysiwyg_imageupload:1281:]]
Rgds / Abilash
Abilash,
When doing a re-baseline programme, first you need to get approval from the Engineer. 2nd you need to ask why you need to rebaseline? Did the original access, sequence, methodology or logic change? or is it a delay recovery measure? if so, then what new measures or strategy will you propose in order to recover the delay?
When doing a rebaseline, you obviously need to discard your original baseline and make your current progamme as your baseline, the actuals or as-built data then becomes your plan upto your last cut-off date and then do your changes in the remaining activities. Once you get approval from the Engineer, this now becomes you new baseline programme.
Good luck,
Daniel