Hello friends,
I have assigned the Actual Date of an activity as 10-july-2012
Now i came to know the activity has not yet started.
When i click the Actual Check box in status. The report comes as,
"Cannot set status to Not Started if activity has actuals"
How can i rectifiy this problem.
Kindly advise.
Regards,
Sivaganesh.
Actual Date of an activity
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
highlight the activity you want to change, go to the status tab, uncheck the finish date, change the physical % complete back to zero, reset the actual & remaining labor units (budgeted quantity)in the labour units box, then you should be able to uncheck the start date, it will ask you Are you sure that you want to change the activity to be Not Started? Jusk click yes and it should work
Scott Hastie
Set the actuals to zero (resources, cost, etc)