Globally assign resource to role

R
Ramon Perry 👤 Member for 13 years 9 months

How do I globally assign a resource to a role, whilst preserving the Budgeted Units, Remaining Units, Remaining Units / Time on the activity?

I tried using Global Change, If Role = Subcontractor A, then resource = Subcontractor A, however the Default units/time from the resource over-writes the remaining units/time in the activity.

I'm on P6 version 7.0

Thanks,

Ramon

A
Arun R 👤 Member for 14 years

Dear All,

                  I what to know is there any internationally accepted standard for work quantity Vs manhour?

For example 50cubic meter concreting needs this much manhour, like that? Please help......I want to know how resourses can be assigned in activities.

D
Dieter Wambach 👤 Member for 19 years 5 months

Hi Ramon

 

in my opinion the best will be to do it role by role:

 

1. Filter by role <x>

2. Open "Assign Resources"

3. Select all activities

4 Check resource for correct default assingment and price, correct if required

5. Assign resource

--> Apart from "2" same procedure for each role. 

 

Good luck with your project!

Dieter 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts