why allways the client is not satisfied with program links.the links between activities ,shop drawins and coordination drwings the program become complicated for MEP activities and civil can any body help me with his experience
program links
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi,
to my knowledge , the links beween the activities has specific logic and sequace based on the method of construction , for example the activity can not be statred without approving the related detailed shop drawings, obtaining No Objection certificates from the cocerned authorities, approval of the materials ,approval of the method statment, have the required resources and finish all the predessor activities which have the relation finish to start with this activity.
the client has to chech the sequance and logic and if it is complining with the normal construction sequance and logic then they have no wright to object in this issue other with the program will be meaninglesss.