Link remaining duration and schedule percent complete problem

Dear Freinds

 

I have a schedule an auto cost rule linke remaining duration and schedule percent complete is unchecked and the schedule culcuates all value based on this situation when i change this (check the box) the remaining duration and pecent complete remain unliked  unless i change one of them manually.

 

How can i recuculate remaing durations based on the percent complete for all activities in the schedule

 

please advise

 

Regards

P
Paul Harris 👤 Member for 25 years 1 month

Try running a global change after backing up you project.

The option only works when you change data not when you turn oin and off the option.

 

Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

www.eh.com.au

www.eastwoodharris.com

www.primavera.com.au - a Primavera scheduling software resources site

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts