Activity Codes

Can anyone tell me if I am perhaps doing something wrong. When I copy an existing project and have selected the 'Activities' check box the newly created copy does not have the codes ! I have had to use a global change into User_text2 and then edit the new projects to get the codes back into the new project.

Thanks

Ronnie.

R
Raymund de Laza 👤 Member for 16 years 6 months

Ronnie,

Global Codes are not going to be copied with ... Copy the Global Activity codes into the Project Activity codes and assign The Project activity codes to the activities ...in this case copied projects will carry the same codes..