Creating Baseline in Primavera P6

Good Morning everyone, I had a quiery in P6 releated to Baseline.

1. How to assign baseline?

2. How to maintain baseline?

3. How to do update progress in assigned baseline? 

A
Ahmed KHR 👤 Member for 15 years 7 months

The probleme is about the Planned dates (P6 consider Basline planned dates and not START/FINISH DATES)

A
Ahmed KHR 👤 Member for 15 years 7 months

Hi Rajah;

 

You can assign baseline by the steps below:

1-Project=>Maintain baseline=>Add (the baseline).

2-Project=>Asign baseline=>select the project wich u have already maintain it in the 1st step.

3-Go to View=>Bars and display the project baseline bar.

Its easy to do it but I have a problem!!!!

The finish date of the activities already started don't correspond to the project wich I choose as Baseline???????!!

Thank you for yours help.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts