Help, % complete doesn't reflect reality

Hi all, i have Project 2003, I'm not an expert and I generally get by (it isn't that important for my job however from time to time it is necessary).

I have a problem that i have one project which has lots of installations, in the beginning requiring more man hours and getting easier toward the end. Currently we are 50% through the projecttimewise but we have installed more than estimated but the % complete column shows much less being based on duration, however the duration really isn't accurate since it might have 10 days for a certain task but that task takes 15 men. Whereas later tasks have 10 days but they are for 1 man. So you see, it doesn't balance out accurately using this method. How the hell can I do it to more accurately reflect the actual completion as opposed to the duration.

As a clear example; if I were to decrease the duration of a task to say 2 days each instead of 16 days the ‘percentage complete’ column of the project would reduce - however completing tasks in a faster time than the duration estimated obviously does not mean that the project is less complete, but rather the opposite. So you see; this column is not a true reflection of the progress so far. Likewise if I were to increase the time it takes to do a task to 20 days each it would increase the ‘% complete’ column.

I'm going nuts here and can't find anything on the web to help. And please keep the jargon for a numpty like me :) 

C
Christopher Amores 👤 Member for 18 years 9 months

James,

 

You have to make a custom formula for the % complete you wish, in your case manhours. You won't be using anymore the Duration % Complete. Apply this formula in the custom field and add it as a column.

Hope this helps.

 

Chris

A
Anoon Iimos 👤 Member for 19 years 8 months

yes of course there are differences in calculating % progress;

if you want to use duration as your factor, then you have to tailor your plan to be adaptable to duration;

otherwise, you can either use resource units and/or cost;

or maybe your own weighting factor;

the software will never tell you what is the right weight factor to use;

you need to find it out yourself,

by the way, I've never seen yet if MSP calculates planned % progress (or based on what factor?).

J
James Morrison 👤 Member for 13 years 9 months

No, that doesn't work, i can't get anymore detailed than I have. I have more than 1000 lines. Unless I break it down into what they do every hour which isn't feasible.

I'll give you a simplified example of the problem:

It takes 10 men 10 days to perform the first task.

It takes 1 man 10 days to perform the second task.

The first task is 100% complete, the second task is 0%. The completion should be 91%, however MS Project says it is 50% (impossible) - it is just calculating from duration (10 days and 10 days) and not taking into account the hours it takes to do it.

S
Shareef Abdul Azeez 👤 Member for 20 years 8 months

There must be other pecentage complete types in MS Poject 2003. I have not used MSP as such can not be specific.

It looks you are using Duration percentage complete (OD-RD)/OD.

In P6 this situation can be handled by performace, units or physical pecentage complete.

 

Regards

Shareef A Azeez

 

A
Anoon Iimos 👤 Member for 19 years 8 months

that's what I'm trying to say,

if you are able to decompose your tasks into a daily duration, then you will get rid of longer duration for a single resource;

then I guess that you will get what you need.

J
James Morrison 👤 Member for 13 years 9 months

I have very detailed tasks and the majority are 100% complete. But I have several tasks lasting many days (for 1 man) which make the duration seem longer in total than the tasks that have been completed. Perhaps there is some settings that need to be altered?

A
Anoon Iimos 👤 Member for 19 years 8 months

I suggest you decompose your task (or activities) to as much details as you can;

the more you got details the more it will become accurate;

if you got details to the minute, then you can allocate your resources (or man-hours) accurately (or maybe nearly).

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts