Weightings

D
Deepak Astagimath 👤 Member for 19 years 10 months

In P3 we have an option of seeing the percent complete as the Duration asweight factor when coputing the percent complete, where in the total sum of Ori Dur and Total sum of Rem Dur are used as weight factor to compute % complete. I have attached a screen shot from P3. formula p3 uses as (OD-RD)/OD. In this each activity duration is considered as weighting factor.

[[wysiwyg_imageupload:1181:]]

I would like to know similar/same option in P6.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Barry,

In P6 you cannot weight your WBS/Activities without cost otherwise your summary band will always have zero %. I recommend using man-hour as cost by setting Price/Unit on resources say $1.00/unit. Alternatively, remove effective date, max unit/time and Price/unit by deleting the data under resource-> Unit & Price tab. The under Project Window-> Calculation tab = enter 1.00 as a default Price/Unit for activities without resource or role Price/Units. This automatically compute your hr or unit = budgeted cost.

B
Barry Fullarton 👤 Member for 17 years 5 months

Guys I appreciate the answers here



However we don’t load costs into our programs here, don’t ask me why?



So I need to "fix" the phases into those percentages, so that when we measure physical progress it measure it against that phase,



We have back ups measure the manhours,



Even if we load hours, I need to ensure that these phases are locked ? at these percentages ?



Who can help

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Barry,

Waseem is correct that Top Down Estimation is another way to weight and spread the cost to WBS and Activities using resource. You need to apply this for each WBS to have accurate distribution and should have only one resource define for each WBS otherwise you need to compute how many units for each resource to arrive on the expected weightings. Also be aware that using top down estimation will possible over allocate your resource max unit/time that prevent user to level the resource.

W
Waseem Saber 👤 Member for 21 years 6 months

Hi Barry,



did you ever tried Top Down Estimate, i think this would be helpful to allocated cost with 90-95% accuracy, i would rather recommed using the top down estimate to spread the cost for the project, the top down estimate works on the weighted Original Duration, say you have 10 activities, each with 10 days duration, thus each activity would we 10% weighted duration and the cost spreading could be done using this weighting.



if you have any further query, send me an email i will forward you the file with the steps.





cheers



W.Saber

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Barry,

P6 use cost to weight WBS and or activities. There a lot of ways of doing it and the best practice is to use budget cost against its WBS and Activities with equivalent Cost Account which is very useful especially for Earned Value Management.

For this exercise if you wanted to weight your WBS/Activities using your own parameter like what you mentioned on the other post.

Example (just for this exercise) say $1000.00

Design -> 10% = $100

Procurement -> 15% = $150

Project Management -> 20% = $200

Construction -> 55% = $550

Total ->100% = $1000



The general idea is to know the value of each WBS that equivalent to the Budgeted Cost At Completion (BAC) that need to distribute for each activity.

On the other thread I mention on how to weight activities using duration if BAC is not available using 3 different options.

For this exercise I would like to use resource loading instead of expenses and or activity status fields.

1)     First create a resource for each WBS so BAC allocated cost can easily distribute with max unit/time = 1 (i.e. Labor)

Ex: Design, Procurement, PM and Construction

2)     Assign resource by highlighting all activities per WBS (i.e. Design WBS) then right click -> Assign-> Resources then double click Design Resource

3)     Repeat until all WBS activities have their own resources

4)     Show the Budgeted Labor Unit column by right click on the activity area window and select column->Unit-> Budgeted Labor Units

5)     On each WBS summary band will have a total number of units based on duration. (i.e. Design = 200 labor units) Use the WBS total unit to get the rates of each resource assigned. (e.g. Design = $100/200 hr or unit = $0.50)

6)     Select Enterprise-> Resources and enter the rate per each resource based on the derived rates per resource.

7)     Show the Budgeted Labor Cost column by right click on the activity area window and select column->Cost-> Budgeted Labor Cost

8)     Check the main summary band if equivalent to $1000.00 and each WBS cost = allocated cost.

9)     If everything is fine and according to what expected… CONGRATULATION!!! You weighted your WBS and Activities successfully.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts