Hi to all I am a junior planning working in oil and gas and doing scheduling.My question is that my company works 10 hours a day and i developed a calender of my company setup up the timing from 6 am- 4:30 pm but when i assing resources and insert work column its show 8 hours even the base calender of resource is my company calender but it shows 8 hours and when i changed it from option setting that company works 50 hours and 10hrs a day that duration chages in decimals like .5 days .8 days. looking for help
Faz
Hi Faz
Check that your work pttern does not have any break time.
Best regards
Mike Testro
Which software u are using and version ?
Regards
SM