To behave ALMOST like P3/P6 on this you need to set some options.
MS project 2010:
File - Options - Advanced - Calculation Options For This Project
Move end of completed parts after status date back to status date (not like P3/6 but you need to set this one to yes, otherwise you cannot select the next one) YES
and move start of remaining parts back to status date (like P3/P6 standard) YES
Move start of remaining parts before status date forward to status date (like P3/P6 standard) YES
and move end of completed parts forward to status date (not like P3/P6, so optional for you) ?
Once you have set these options, you can schedule thr project with
Project - Update Project - Reschedule uncompleted work to start after (type in status date)
These settings will make any project planner who moved from P3/6 ro MS Project very happy.
To behave ALMOST like P3/P6 on this you need to set some options.
MS project 2010:
File - Options - Advanced - Calculation Options For This Project
Move end of completed parts after status date back to status date (not like P3/6 but you need to set this one to yes, otherwise you cannot select the next one) YES
and move start of remaining parts back to status date (like P3/P6 standard) YES
Move start of remaining parts before status date forward to status date (like P3/P6 standard) YES
and move end of completed parts forward to status date (not like P3/P6, so optional for you) ?
Once you have set these options, you can schedule thr project with
Project - Update Project - Reschedule uncompleted work to start after (type in status date)
These settings will make any project planner who moved from P3/6 ro MS Project very happy.
I need to know the status of any project on some earlier dates. I tried changing status date. The mode of calculation was set to automatic. There were no changes observed. I was not able to get the % complete of each task as on the status date. Is there any way to get all details of my project as on a particular Date..
The reason MSP does not do anything automatically just because you set a status date is because it is waiting for you to tell it what happened. It doesnt have eyes or legs and it cannot go to the site and have a look at the job and it cannot read the site records, but you can. Only you know if the task has started and when. Only you know whether the task has been in progress continuously up to the status date, or whether it was interrupted, or what the actual duration is, or what the actual finish date was if the task is finished, or what the remaining duration estimate is.
This general idea is as applicable for P3 as it is for MSP.
If you have been actualising tasks in P3 with one click of a button you have been allowing or forcing the software to make a lot of assumptions which are probably not correct.
Have the Tracking Toolbar visible/available (View, Toolbars etc).
Switch to the Tracking Gantt View.
Switch to the Tracking Table (View, Table etc).
Make the Status Date vertical red line in the tracking gantt chart (Format Gridlines).
Select the task that you are interested in.
Click the 2nd button from the left on the Tracking Toolbar.
That will do for now but there is a bit more to it if the task actual start date, actual duration and actual finish date are not the same as planned, or if the task was not continuously in progress up to the status date, or if the actual work or actual cost are not as planned.
Let us know how you get on up to this point.
BTW, I have described this simple and effective procedure about 1000 times, often with more detailed explanation, both here and at the newsgroup microsoft.public.project.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
To behave ALMOST like P3/P6 on this you need to set some options.
MS project 2010:
File - Options - Advanced - Calculation Options For This Project
Once you have set these options, you can schedule thr project with
Project - Update Project - Reschedule uncompleted work to start after (type in status date)
These settings will make any project planner who moved from P3/6 ro MS Project very happy.
To behave ALMOST like P3/P6 on this you need to set some options.
MS project 2010:
File - Options - Advanced - Calculation Options For This Project
Once you have set these options, you can schedule thr project with
Project - Update Project - Reschedule uncompleted work to start after (type in status date)
These settings will make any project planner who moved from P3/6 ro MS Project very happy.
Hi everybody..
I need to know the status of any project on some earlier dates. I tried changing status date. The mode of calculation was set to automatic. There were no changes observed. I was not able to get the % complete of each task as on the status date. Is there any way to get all details of my project as on a particular Date..
Thanks & Regards
The reason MSP does not do anything automatically just because you set a status date is because it is waiting for you to tell it what happened. It doesnt have eyes or legs and it cannot go to the site and have a look at the job and it cannot read the site records, but you can. Only you know if the task has started and when. Only you know whether the task has been in progress continuously up to the status date, or whether it was interrupted, or what the actual duration is, or what the actual finish date was if the task is finished, or what the remaining duration estimate is.
This general idea is as applicable for P3 as it is for MSP.
If you have been actualising tasks in P3 with one click of a button you have been allowing or forcing the software to make a lot of assumptions which are probably not correct.
Set the Status Date, as you have done.
Set a Baseline (Tools, Tracking, Baseline)
Have the Tracking Toolbar visible/available (View, Toolbars etc).
Switch to the Tracking Gantt View.
Switch to the Tracking Table (View, Table etc).
Make the Status Date vertical red line in the tracking gantt chart (Format Gridlines).
Select the task that you are interested in.
Click the 2nd button from the left on the Tracking Toolbar.
That will do for now but there is a bit more to it if the task actual start date, actual duration and actual finish date are not the same as planned, or if the task was not continuously in progress up to the status date, or if the actual work or actual cost are not as planned.
Let us know how you get on up to this point.
BTW, I have described this simple and effective procedure about 1000 times, often with more detailed explanation, both here and at the newsgroup microsoft.public.project.
Try a search.
hi
try this
tools - tracking update task
and
tools - tracking update project