Hi Experts; Our project was extended to 31st July but due to lack of funds from the client it has been delayed again.I submitted the schedule to the client woth a new Expected finish date.In reply to my EOT,I received the Following reply from the client.Can anybody explain me that what exactly our client wants from me.Please read below; .....The current overall percentage progress as per the calculations sent by you and the new completion dates sent be Essam are as follows: Completion Exp. FinishB09&10: 52.10% 12-01-2014 B011: 58.90% 11-06-2013The percentage completion provided to the insurers for last extensions (upto 31 July) during Feb. 2012 were 49% for B09&10 and 57% for B11. So it appears we had very slow progress during last five months perhaps almost dormant construction activity for the subject buildings. The extensions required based on the above completion dates (sent by Essam) will be 18 months for B09&10 and 11 months for B11 and this will involve substantial premium. Please send me a break-up of the above extension period based on construction activity i.e. dormant months, low activity and high construction activity so I can try for some reduction of premium at least for the dormant months. REgards, SM
Dear Shareef Abdul Azeez
Thank you for your kind reply.Can you please explain that how it will be shown in activity usage spreadsheet.The said schedule is not loaded with manhours or man-months.And what doest High activity and low activity means?? Does it mean the predecessor and successor?
Regards
Hello
If you use an activity usage spread sheet the low activity and high activity usage months can be assertained.
I am confused about this line:
Please send me a break-up of the above extension period based on construction activity i.e. dormant months, low activity and high construction activity so I can try for some reduction of premium at least for the dormant months.
I do not understand the Low activity and high activity.what are these that he is referring to?
Regards