Hi to all!
I just encountered this kind of situation that's why I need some clarification and ideas regarding 0/100 Percent Complete.
What I know is that, 0/100 Percent Complete is applicable only for performance percent complete which is "Actual Progress or Earned Progress". So, Is this also applies in getting the planned value to date?
I always believe that whatever application we are going to use in getting actual progress must be the same method or system in getting a planned progress, and not to compare the apple to mango.
I hope to get help here in clarifying the issue.
Thank you & More Power to Everyone!
clintmarqz
:D
Thank you Nader and more power to planning planet team.
Dear Clint,
That’s right, planned progress does not have as many options as actual progress [in P6], and you cannot have the exact same pattern in those two. This causes some false variations between the two values (you may still have SV<>0 when you are doing exactly as planned).
However, I’ve tested some scenarios and realized that the false variation is less than 0.5% in all of my detailed plans (with more than 4000 activities).
Best Regards
- Nader