Hi, I am very new the p6, i need to crete a Cash flow report for the projec. I have problem recording the budget income that we are going to receive during the life time of the project. Can I record the monthly budget project income in p6?, also i could not find any layout realted to cash flow. please advise me how to do it,, thank you very much :):) cupid
I guess you already figured out that if expenses are of positive value then income is of negative value and the rest shall follow.
Best regards,
Rafael
as stated by Anoon, the best way is to code your activities using the expense tab then go to the Tracking module and set up your flow report.
Charry,
If you have a liscenced copy of P6, you should contact Oracle to get a manual.
If you don't have a licenced copy of P6, you should get one.
Software manuals are copyrighted document, and distributing them without the owner's permission is copyright theft. We do not allow that on this site.
if you have pls email and send it to [email removed by moderator]
thanks a lot in advance....
charry
try using the Expense tab; and then go tracking view
Hi Cynthia
All my current activities are based on the "cost" of the Labour, Non Labour and materials. We are a sub contractor, we invoice our customers when we completed an activity. My manager wanted me to show a column, for example "Income", or "budget income" on each activies, so that he will be able to see the profitility of each activity... I am not sure how to do it in p6 ...
Thank you
I use cash flow to show planned cost through the project - but I'm not sure there is a place for income. Are you trying to cash flow the cost?