Adding Resources to Multiple P6 Projects

Is there a smart way to add a set of roles to multiple projects ? I have a set of about 20 Roles that need to be added to a WBS summary on about 50 projects. I did see some reference to 'Group' in the manual but couldn't find any detail. It may not even be what I was thinking or hoping it was where I could in effect add a set of roles rather than individually. Any help would be appreciated.

Thanks

Ronnie.

D
David Kelly 👤 Member for 21 years 7 months

I would open all the projects, filter the WBS activities, and use the "Assign roles to selected" button in the Command Bar on the right of the screen.  CTRL-Click works to select multiple Roles - so a full many-to-many link can be made