You need to go "Library Explorer". Under "Currency Unit" you can add unlimited currency. When you add new currency you also enter exchange rate.
After that it is all up to you.
1) you can right click on activity table such as excel and from Format Cells you can choose which currency you want to display. It will automatically convert new currency using by exchange rate.
2) I am not sure if you know in ASTA the same Column can be display on activity table more than once. For example you select cost and add twice to table. After that you right click on Colum and from table definition you can select one USD another EURO. The same activity and on the same cost you will display both currency.
If my answer is not cover your expectation please follow up Mike’s recommend. If help not cover your expectation ask to Mike who is GRU of ASTA and Project Management, I am sure he will know the answer J
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Raphael,
You need to go "Library Explorer". Under "Currency Unit" you can add unlimited currency. When you add new currency you also enter exchange rate.
After that it is all up to you.
1) you can right click on activity table such as excel and from Format Cells you can choose which currency you want to display. It will automatically convert new currency using by exchange rate.
2) I am not sure if you know in ASTA the same Column can be display on activity table more than once. For example you select cost and add twice to table. After that you right click on Colum and from table definition you can select one USD another EURO. The same activity and on the same cost you will display both currency.
If my answer is not cover your expectation please follow up Mike’s recommend. If help not cover your expectation ask to Mike who is GRU of ASTA and Project Management, I am sure he will know the answer J
Tekin
Hi Raphael
Welcome to planning planet.
Go to Help
Type currencies tick Display
Select the first on the list and you will find all the information you need.
Asta Help is much quicker than the PP forum.
Best regards
Mike Testro