Is it possible to disable F9 in P3

Member for

14 years 1 month

Hi Martin,

F9: to calculate your schedule, make sure you have set the Autocost rules in accordance. You may have choosen to have P3 automatically schedule whenever you change data that affect calculated schedule dates.

I do not know of a possibilty to disable F9 in P3.

Maybe a windows option somewhere that overrules your F9?

Hope you find it.

Regards,