F9: to calculate your schedule, make sure you have set the Autocost rules in accordance. You may have choosen to have P3 automatically schedule whenever you change data that affect calculated schedule dates.
I do not know of a possibilty to disable F9 in P3.
Maybe a windows option somewhere that overrules your F9?
Member for
14 years 1 monthHi Martin, F9: to calculate
Hi Martin,
F9: to calculate your schedule, make sure you have set the Autocost rules in accordance. You may have choosen to have P3 automatically schedule whenever you change data that affect calculated schedule dates.
I do not know of a possibilty to disable F9 in P3.
Maybe a windows option somewhere that overrules your F9?
Hope you find it.
Regards,
Arend