Anyone done a shutdown project using Asta before??

C
Craig Adams 👤 Member for 14 years 5 months

Have the possibility of joining a Mining shutdown 3 weeks out from start, anyone had this experience / exposure before?

Schedule exists in MSP (only seen PDF copy so far) but I'd like to use Asta.

Any assistance / advice appreciated.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Mike,

it was but was less known than today. So it is not strange that 10 years ago you did not not know about its capabilities.

Spider Project was used for Caspian Pipeline Construction planning 15 years ago and was used for shutdown planning before and after.

Regards,

Vladimir

 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Vladimir

Good point but I don't think Spider was widly available 8 years ago.

Best regards

Mike Testro

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Mike,

PowerProject is not the only available option. You forgot about Spider.

The rest is right.

Best Regards,

Vladimir

M
Mike Testro 👤 Member for 20 years 5 months

Hi Craig

I was involved in a similar project when planning the switchover from one old district sub station to a new one.

I was the planner for the contractor and EDF asked me to plan the switchover in P3. (MSP would be worse)

I soon convinced them that since the time unit was to be in minutes PowerProject was the only available option.

With one of the EDF engineers at my shoulder it took me three days to get the sequences and resources balanced using at least 6 work patterns and three calendars.

So yes it can be done as long as you are with someone who knows how it is done.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts