Dear All Planner,
My company testerday asked me to analysis on our subcontractor manhours peak and associated manpower curve..
Any information how I can do thjat using P6??
Thank you all,
HANSON
Dear All Planner,
My company testerday asked me to analysis on our subcontractor manhours peak and associated manpower curve..
Any information how I can do thjat using P6??
Thank you all,
HANSON
Draw the Man-Hour S-curve , then compare with the provided man powewr schedule for each sub-contractor .
Chris,
Thank you very much and YES, I do have electronic copy and I can send it to you if you don't mind?
Thank you,
HANSON
Make a histogram and you will see if from there.