Dear All,
How can we generate a cumulative late curve from the resource usage spread sheet
in P6. Your valuable remarks are highly acceptable..
Regards.
Sunil.
Dear All,
How can we generate a cumulative late curve from the resource usage spread sheet
in P6. Your valuable remarks are highly acceptable..
Regards.
Sunil.
Hi Wynand,
Thx for this info..
Sunil.
Hi Mike,
Thx for this info...
Hi Wynand
Why not just add the day total float to the ASAP date.
Best regards
Mike Testro
I will put a finish as late as possible constraint on all the the task export the timescale data to excel , that is how i do it in Microsoft Projects 2010, not to sure how in P6 , hope it helps.