Planning process is linear or is iterative?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Ahmed,
the same may be done using project management software.
Why do you need Excel?
Dear planners;
I want to share our experience in monitoring progress for Railway/Line projects.
for my self I'm using excel (Multiple columns: Km ponits each 5m; zones; area; phases of work; date of achievement of each phase on each Km..) so I can have Three results; Graphical of the progress; Progress by Zone (Area) with possibility to choice the cut off date (Can get the progress on older dates); and the cumulative progress by months or week.
I found this method very useful and easy, please if you have another methods please share.
Gary wrote;
"The plan itself would be linear.
The planning process however is iterative."
Can I nominate the above for the "Favorite quotes about planning" thread? :-)
I basically agree with Gary. However, there are certain occasions when the plan is also not totally linear: when rework has to be performed after a failed test.
If the rework has been pre-planned in fragnet form (as it should have been), then in a sense the plan is still linear. but the "product" has to go through reiteration.
Them semantics things is a bitch, aint they?
Fraternally in PM,
Steve D.
I think were talking at cross purposes here.
The plan itself would be linear.
The planning process however is iterative
Hi All
I cant help but jump in here.
A fully developed bottom up plan with FS links and one critical path is Linear.
It can be nothing else.
Even when progress is added the linear nature is retained.
In PowerProject there is the option to "Link Around Completed Tasks"
Best regards
Mike Testro
Many thanks Gary..
Any time you enter information, analyse it, make changes, then re-analyse, its an iterative process. Planning is definitely an iterative process
example (when developing a schedule):
"Weve got 10km of pipe to put in the ground. How long will that take?"
"4 weeks"
".....thats no good. That pushes us past contract completion"
"OK, I guess well have to hire an additional welding crew. That would bring it down to 2 weeks"
"perfect"
...is an iterative process.
example (when updating a schedule):
"The pump is going to be delivered 2 weeks later than planned -shipment has been delayed by adverse weather"
"Oh dear. That was on the critical path. Is there anything we can do to recover the delay?"
"Well the diesel gen is due in 1 week. we could recover some of it by installing that first, if we can get the foundation done in time."
"OK, pull the boys off the pump foundation, and get them cracking on the diesel gen. Pull extra manpower from the admin building if you need to"
...is an iterative process
hmmmmmmmm
what do you mean by Linear vs Iterative.
There is the answer to the question,
If you are using CPM (90%), then it is linear.
Regards,
Safak
But with respect I do hear what you say!!
Roger
Have you not forgotten singing off the same hymn sheet, or even project cosmic view, or even taking the low hanging fruit
Regards
Roger
Hi Tom,
I can imagine many people enjoy reading your programme narrative.
Cheers,
Most of my planning is "out of the box", with a degree of blue sky thinking. If we are not all on the same page then I run it up the flagpole and see who salutes. However we MUST reach out for an end to end solution. To touch base together, aim for evolution NOT revolution.
REMEMBER TEAMWORK MAKES THE DREAM WORK !