Trouble with Overtime Rates

I have a resource eg  rigger working 8 hrs a day(9am to 5pm) for Rs.300/day as standard. I gove him an overtime rate of Rs.90 per hour.

Lets say i have an activity which is planned for one day having this rigger as a resource, the planned cost of the activity is Rs.300.

But if the actual duration is 10 hours (9am to 7pm) then i am strugling to get the right acctual cost displayed for that activity.

Need Help in Understanding the overtime calculations and how should i anter the actual duration or work so that the overtime will be appropiately calculated.

E
Edwin Raj 👤 Member for 14 years

i'm having confussion where to enter in resource usage sheet

Please clarify..

A
Abdullah Merchant 👤 Member for 15 years 6 months

Hi Ismet,

 

Thank you so much for the help. I did try it and was content with the results. However when i go to the Task Usage i see the various resources underneath, and then if i update lets say 14 hours of actual on a particular day, then all the other resources for the same day get updated for the same amount too. Although i can go back and delete it from the other days, but why do all the other resources get updated even for the other days.

Ill could send you a scehdule that i had sampled, to practise this work update.

 

Regards,

Abdullah.  

I
Ismet Kocaman 👤 Member for 16 years 3 months

In Project, Overtime work is part of the Total work. That means Work = Regular Work + Overtime Work. If there is no Overtime work then Work is equal to Regular work. Overtime work is the work outside of the resource calendar.

To complete the 8-hour duration task you can enter 8 hrs for Actual Work and then 2 hrs for Actual Overtime Work. Project will then calculate Actual Work (= 10 hrs) and Regular Work (=8 hrs). You can of course add these detail fields (Actual Work, Actual Overtime Work, Regular Work) to the timephased part of a Resource Usage view. The Actual Cost will be calculated as follows:

Assuming Hours Per Day setting is 8 hours;

                         Actual Cost = 300 Rs/d * 1d + 90 Rs/h * 2hrs = 480 Rs

I hope this is what you are looking for. Pls give us feedback on your progress.

--Ismet

Forum Sponsor

Top Posters

GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts