Does the resource graph represent the baseline plan and the actual+forecast?
Vico Control2009SP3 resource graph behavior
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
I made a simple test:move Laborer resources from week1 to week 2; current 18 laborers
* in control mode
* move 5 days SWEEP fiberroll
* move 3 days sweep silt
* change to design mode
* refresh and reforecast
* change back to control mode
The result: still 18 laborers but it looks like something changed
Conclusion: I will test more