Does the resource graph represent the baseline plan and the actual+forecast?
Vico Control2009SP3 resource graph behavior
Forum Sponsor
Top Posters
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
I made a simple test:move Laborer resources from week1 to week 2; current 18 laborers
* in control mode
* move 5 days SWEEP fiberroll
* move 3 days sweep silt
* change to design mode
* refresh and reforecast
* change back to control mode
The result: still 18 laborers but it looks like something changed
Conclusion: I will test more