copying Resource Assignment from Primavera to Excel

S
SM PUM 👤 Member for 14 years 6 months

Dear All

Caan anyone please suggest me solution for the following issue;

I am working in Primavera P6 Version 8.From resource assignment I am not able to copy the Total bugheted units from Primavera to excel.When I was using version 6 I used to check the Total and "Show summary" options,then by pressing ctrl c and ctrl v I copy the required data to excel.But in version 8 It is not happening.In activity usage spreadsheet window it is possible but in Resource assignment window it is not working.Can anyone using version 8 please check out this problem and tell me the solution

 

I shall be grateful

Regards