Critical activities more than non-critical

S
SM PUM 👤 Member for 14 years 6 months

Hi planners

I have submitted a schedule to my manager and he has returned it with following comments;

Critical Activities are more than non Critical Activities. Try to minimize these critical activities.

 

Please Advice

M
Mike Testro 👤 Member for 20 years 5 months

Hi Hall

If you have a programme that has a start point and a clear cascade of tasks to an end point then there will be only one critical path.

If there is more than one CP then the chances of this occurring naturally are infinitesimal - therefore the most likely answer is the programme has been rigged.

You can of course have a number of such sectional cascades in a single programme.

Best regards

Mike Testro

M
Mike Testro 👤 Member for 20 years 5 months

Hi SM

You can start by removing all constraints that force criticality.

Next check how many tasks are set ALAP - they show critical even when there have lots of float.

After that look at what critical tasks remain and if more that 50% look to find out why -

First review any tasks more that 20 days long

Next check tasks with more than 1 outgoing link - are they all necessary?

Finally there an only be one critical path - if you have more than 1 youre programme has been rigged.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts