effect of mile stone on scheduling

S
Sunil Babu 👤 Member for 15 years 6 months

Hi Friends,

If we put some milestones for some activity start in WBS levels...will it affect

any problem while scheduling..will it make any effect in activity floats..?

your views are most welcome.

Regards

Sunil.

R
Rafael Davila 👤 Member for 22 years 3 months

Milestones are activities and as such they might have an impact on the successors. They are not always dummy links only good to highlight some events, they can even be driven by their own calendar, can be assigned costs and even resources. Yes even resources and this might have an impact on resource leveling even when the demand of the resource is for 0 time, here might be very dependent on your specific software.

It is common to use contractual milestones and set a finish constraint to the milestone to show up criticality on intermediate contractual milestones. They can affect how float is displayed up to the point to create negative float and make late dates earlier than early dates if your software uses pseudo mathematical algorithms that break the rules of physics (wrong modeling).

Please note that I am not telling that the use of constraint to show criticality is wrong, but that the implementation by some software can be wrong.

In the following figure you might see how different milestone settings will have. Take particular attention to Milestone at phase 4 that has an unattained finish NLT (no-latter-than) constraint, the software displays it critical ( 0 float) but did not fooled the laws of physics by making late earlier than late dates, therefore it did not created negative float and will never yield S curves where Late Curve at a portion or at the whole will be on top of the early curve an incomprehensible pseudo mathematical result. 

Photobucket

Best regards,

Rafael

D
Daniel Limson 👤 Member for 24 years 7 months

Sunil,

I dont think you can put, add  or create a Milestone in the WBS level. You can only add a milestone at the activity level.

A milestone (start or finish) has a zero duration so there is no effect to subsequent activities in terms of float. It is actually a good idea to add a start milestone to a group of activities especially relating to access dates or interface dates.

Cheers,

Daniel

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts